our essential task as project manager, at this point, is to determine dependencies; that is, activities that can't be started until others have been completed.
akorolchenkoje citiraoпрошле године
list of activities into a logical sequence based on your experience.
akorolchenkoje citiraoпрошле године
Backing up your files to a cloud service, like Dropbox, or to an external drive mitigates the risk of losing all your work.
akorolchenkoje citiraoпрошле године
OK, let's see what that might look like.
akorolchenkoje citiraoпрошле године
Summing up estimates, it will take about 75 working hours, or 13 six hour days, to complete the project.
akorolchenkoje citiraoпрошле године
Any delay in meeting a critical date will extend the time it takes to complete the project
akorolchenkoje citiraoпрошле године
Summing up estimates, it will take about 12 working hours to complete this project.
akorolchenkoje citiraoпрошле године
The biggest challenge I've encountered with this type of project is getting the correct spelling for people's names and their current contact details.
eapostovalovaje citiraoпрошле године
This information is detailed in a document with a name like concept brief, project submission or business specifications.
eapostovalovaje citiraoпрошле године
Study the document defining the project. Meet with the project owner and obtain agreement that you have understood the task, and any constraints the owner has imposed.