bookmate game
en
Knjige
Peter Mulraney

Everyday Project Management

  • b2509333234je citiraoпре 5 месеци
    In large organisations, a project generally doesn't get onto the drawing board until the person proposing it has clearly defined what the project is about, and identified the desired outcomes the project must deliver within defined cost and time constraints.
  • b2509333234je citiraoпре 5 месеци
    imply due to a lack of detail or a failure to provide a clear description of the desired outcomes.
  • akorolchenkoje citiraoпре 2 године
    our essential task as project manager, at this point, is to determine dependencies; that is, activities that can't be started until others have been completed.
  • akorolchenkoje citiraoпре 2 године
    list of activities into a logical sequence based on your experience.
  • akorolchenkoje citiraoпре 2 године
    Backing up your files to a cloud service, like Dropbox, or to an external drive mitigates the risk of losing all your work.
  • akorolchenkoje citiraoпре 2 године
    OK, let's see what that might look like.
  • akorolchenkoje citiraoпре 2 године
    Summing up estimates, it will take about 75 working hours, or 13 six hour days, to complete the project.
  • akorolchenkoje citiraoпре 2 године
    Any delay in meeting a critical date will extend the time it takes to complete the project
  • akorolchenkoje citiraoпре 2 године
    Summing up estimates, it will take about 12 working hours to complete this project.
  • akorolchenkoje citiraoпре 2 године
    The biggest challenge I've encountered with this type of project is getting the correct spelling for people's names and their current contact details.
fb2epub
Prevucite i otpustite datoteke (ne više od 5 odjednom)